As the war between the Nigerian Ports Authority (NPA) and BUA terminal, operator of Terminal B, Rivers Port Complex, Port Harcourt rages, the Authority yesterday said  the operators berthed  117 vessels in 18 months without interference after obtaining court injunction from the court.

In a press statement made available to newsmen by the General Manager, Corporate and Strategic Communications, Engr. Adam’s Jatto,the NPA reiterated that it decommissioned the BUA terminal, Portharcourt for safety reasons.

according to the statement, within the 18-month period between January 2018 when the injunction was secured and June 2019 when the Authority decommissioned Terminal B for safety concerns, the group received both liquid and dry cargoes.

The statement read, “It is curious that BUA has continued to insist that the NPA has ran foul of the injunction granted by the Federal High Court, Lagos, because there is no truth in this. Within the 18-month period between January 2018 when the injunction was secured and June 2019 when the Authority decommissioned Terminal B for safety concerns, BUA enjoyed peaceful occupation of the premises and berthed 117 VESSELS made up of liquid and dry bulk cargos! This puts a lie to every attempt to suggest that the NPA has flouted the orders of a court of law.  Moreso, the total number of vessels berthed showed that they have been making full commercial use of the terminal even with the poor quay walls and low draft.

“BUA enjoyed peaceful occupation of the premises and berthed 117 vessels  made up of liquid and dry bulk cargos! This puts a lie to every attempt to suggest that the NPA has flouted the orders of a court of law.”

The statement further put a lie to BUA’s statement that they wrote the authority for the remedial work without approval.

“Bua Ports and Terminals Limited also claimed to have written several requests for approval to perform remedial works on the berth. This is a laughable claim as BUA only commenced writing the authority requesting to reconstruct the berth after the termination notice had been issued following 10 years of refusal to fulfil this obligation. How can you request to reconstruct a berth which you have no legal claim to following the termination? This is yet another of their attempts at deceiving the Nigerian public.

“In the latest press release, the company, while not repudiating the authority’s assertion that they have neglected to honour some of the terms of the concession agreement, alleged that the failure is a result of the NPA’s refusal to fulfil certain obligations.
They name these obligations to include: refusal to abide by a court order, provision of security, dredging of the port, repair, renew and rebuild quay walls.

“Bua Ports and Terminals Limited also claimed to have written several requests for approval to perform remedial works on the berth. This is a laughable claim as BUA only commenced writing the authority requesting to reconstruct the berth after the termination notice had been issued following 10 years of refusal to fulfil this obligation. How can you request to reconstruct a berth which you have no legal claim to following the termination? This is yet another of their attempts at deceiving the Nigerian public.
“On the provision of security, the absence of which BUA alleged: “led to the nefarious activities of hoodlums and vandals who over a period of time cut the pipes and steel beams of the berths thereby affecting their stability and consequently making remedial works imperative,” the Authority wishes to state that we have a record of three reported cases between 2014 and 2016, TEN YEARS after BUA was supposed to have commenced  and concluded the reconstruction works. These acts of vandalism, (which were recorded on August 25, 2014 at 17:45 hours, June 27, 2016 and August 11, 2016 at 2:00 hours respectively) would not have happened if the company had complied with the agreement and conducted the reconstruction within 90 DAYS stipulated within the concession agreement as the collapsed state of the berth exposed the structures and allowed for the cutting. Nevertheless, the Authority is committed to continuously secure the berths despite these isolated cases.”

“For the avoidance of doubt, the decision to decommission Rivers Ports Terminal was out of safety concerns. This concern resulted from a May 16, 2019 BUA Ports and Terminals Limited letter informing us that the “jetty is in a state of total dilapidation and in urgent need of repair or reconstruction…our engineers have advised us that the jetty is liable to collapse at any moment…”

“The NPA would be an irresponsible organisation to look the other way and endanger the lives of Nigerians when a company painted this frightening situation in a letter sent to the Authority.

“The Authority is, of course, prepared to diligently pursue the arbitration process, which it initiated despite the delay by BUA.  This continued media show cannot be used as a ploy to hamstring the NPA from performing its rightful oversight duties and protest the integrity of the Nigerian maritime industry.”

© 2019, maritimemag. All rights reserved.

Pirates escape from bulker off Pulau Cula

Previous article

All hail NIMASA! 

Next article

You may also like

Comments

Comments are closed.

More in Headlines